Step 8: Approval of Design, and Cost Estimate
Step 8: Approval of Design, and Cost Estimate
The engineering cost estimate shall be approved by the competent authority, refer ▬► PPR 2007, Rule 14, Sub-Rule(1) page 13
14. Approval of Cost Estimate:
(1) The cost estimate prepared under Rules 10, 11 and 13 shall be required to be approved by the following authority:-
- Cost estimate from twenty five thousand Rupees to five million Rupees- by the Gazetted Third Class Office chief,
- Cost estimate of up to ten million Rupees- by the Gazetted Second Class Office chief,
- Cost estimate of up to thirty million Rupees- by the Gazetted First Class Office chief,
- Cost estimate of an amount whatsoever above thirty million Rupees by the Departmental head.
- Cost estimate of up to one hundred thousand Rupees- by the Chief of the Office of gazetted third class,
- Cost estimate of up to five hundred thousand Rupees- by the Chief of the Office of gazetted second class,
- Cost estimate of up to one million Rupees- by the Chief of the Office of gazetted first class,
- Cost estimate of an amount whatsoever above one million Rupees- by the Departmental head.
(4) Notwithstanding anything contained elsewhere in this Rule, the secretary or administrative chief of a constitutional organ or body, ministry, secretariat and other offices of similar nature may approve the cost estimate of any amount whatsoever for the procurement of his/her office.