8.CONTRACT ADMINISTRATION, CONFLICT MANAGEMENT, CLAIMS AND DISPUTE HANDLING
Contract administration of the bridge works,
including new construction and major maintenance works, is carried out either
by appointing a Consultant or by the Employer’s own Supervision Team. In both
cases, there will be a Project Management Team within the Employer’s organisation. The term Consultant is used to mean the
Engineer or Employer’s Representative.
The term Project Manager is applied to the person appointed by the
executing /implementing agency. The term Team Leader is applied to the
Consultant’s Chief Resident Engineer whose duty it is to administer the
contracts, with limitations on financial authority where prior approval of the
Employer shall be required. Those limitations concern the issue of a
Commencement Order to the Contractor; approval of the Program of Works, approval
of any sub-contracting of works by the Contractor, quantity variation,
extension of time, interim payment of certificates, final payment and release
of retention money, and performance securities.