Example of Environmental Management Plan of Bridge Project – Sunkoshi Bridge
Environmental
Issues/
Component |
Remedial Measures |
Approx
Location |
Time
frame |
Mitigation
Cost
NRs |
Institutional Responsibility |
|
Implementation |
Supervision |
|||||
Impacts Associated with Location and
Design |
|
|
|
|
|
|
Location of
Borrow Pits and Quarry Sites |
·
Borrow
pit sites must be chosen in areas where water logging problems will not occur
in the future
·
Borrow
pits must be located in lands where the effect would be temporary and
generally involve lower value land.
·
For
quarries, where alternative sites are available, the lowest value production
land must be selected
·
The
aggregate crushing plants should be away from settlement areas and pollution
control mechanisms need to be installed. |
All locations of selected river beds,
quarries and borrow pits determined at detailed design stage |
During the design stage |
Include in
design |
Design Consultant and Contractor |
PIU, DOR / GESU |
Impacts Associated with Construction Stage |
|
|
|
|
|
|
Stockpiling of
Construction Materials
|
·
Land
for the stockpiling of construction materials must be suitably selected such
that it does not occupy private land and affect agricultural lands
·
Clean
area promptly after completion
·
The
storage areas should not be located less than 500 metres from water bodies |
Stockpiling
sites |
Construction
stage |
Include in
design |
Design Consultant and Contractor |
PIU, DOR / GESU |
Blasting |
·
Seek
approval for blasting from the Supervising Consultant.
·
Restrict
all blasting to the hours of 9:00 – 16:30.
·
Conduct
controlled blasting complying with rules under Explosives Act (1961). Prior
notice shall be given to all local residents and the VDC.
·
Inspect
and approve blasting where significant hard rock occurs. Inspect blasting
operation during the course of construction. |
Location of blasting sites. |
Construction |
Construction contract |
Contractor
DSC
|
DSC, PD/DOR
PD/DOR |
Air Pollution
|
·
The
bitumen heating plants need to be established where the effects are minimal
on the surrounding inhabitants
·
Bitumen
heating plants should have in‑built in
mechanisms and facilities for the absorption of gases
·
The
contractor will be required to minimize dust during the construction by
sprinkling water regularly especially in the inhabitants areas
·
In
the areas nearby the school, the works should be done only after school |
Project area,
crushing plants, bitumen heating plants |
Construction
stage |
Include in
design |
Contractor |
PIU, DOR / GESU |
Noise Pollution and Vibration Effect
|
·
Attempts
have to be made to operate heavy construction equipment away from the
settlement areas as far as possible during the day time only. Cracks caused
by vibration need to be monitored closely. If such problems arise, an
alternative method has to be employed.
·
For
the safety of construction workers,
masks, earplugs, hard hats, boots etc. must be provided while on duty.
·
If
the use of heavy equipment is required nearby the school’s, clinic, the
contractor needs to obtain permission from the school’s principal and the
head of the medical clinic
|
Project area,
crushing plants, bitumen heating plants
|
Construction
stage |
Include in
design |
Contractor |
PIU, DOR / GESU |
Water Pollution |
·
Safe
disposal of wastes |
Subproject area |
Construction |
|
Contractor |
PIU, DOR / GESU |
Stress on Public Utilities
|
·
The
Contractor needs to arrange for sufficient water supply and proper sanitation
facilities for its labour force. Separate arrangements are necessary for work
and labour camps.
·
No
labour/worker camps allowed to be located nearby water bodies |
Subproject area, labor Camp, |
Construc-tion stage |
Include in detailed design |
Contractor |
PIU, DOR / GESU |
Nuisance from Construction Camps |
·
The
Engineer must instruct the Contractor to avoid any water related problems
during construction works. The Contractor
should ensure that local water supply does not become contaminated by
use of cement, bitumen etc.
·
The
timely and proper disposal of the solid wastes would be the responsibility of
the Contractor. |
Construction and labor camps |
Construction stage |
Include in detailed design |
Contractor |
PIU, DOR / GESU |
Accident Risk and Road Safety
|
·
Information
signboards should be placed as precautionary measures.
·
Special
measures need to be adopted by contractor for construction works nearby
public facilities
|
Subproject area |
Pre-construction and construction stage |
30,000
|
Design Consultant and Contractor |
PIU,
DOR / GESU |
Occupational Health and Safety
|
·
Protective
clothing including hard hats, boots and
gloves should be provided to the labourers
·
At
every work place, a readily available first aid unit including an adequate
supply of dressing materials should be provided
|
Subproject area |
Construction stage |
Include in detailed design |
Contractor |
PIU, DOR / GESU |
Impacts
Associated with Operational Stage |
|
|
|
|
|
|
Air and Noise Pollution |
·
Provide
signs and speed restrictions on the road sections within dense settlements to
reduce vehicle speed and dust generation
·
Plant
trees as a barrier between the road and the settlements
·
Strict
enforcement of vehicle emission standards |
Subproject area |
Operation stage |
Include in detailed design |
Design Consultant,
Department of. Transport Management,
Traffic Police |
PIU, DOR / GESU |
Accident Risk and Road Safety |
·
Speed
must be controlled by putting up speed limit signs and enforcing them. |
Project Area |
Operation stage |
Include in detailed design |
Design Consultant DOR |
PIU, DOR / GEU |