Step 4: New Rates

If work corresponds to an item description in the BoQ, and if, in the opinion of the Project Manager the timing of the work execution does not impact the cost per unit, or the quantity does not impact the threshold for rate revision as stated in Cl 37.1 (see Rate Variation – Clause 37.1 paragraph below), rates set in the Contract shall be used. If the nature or timing of the work does not correspond with items in the BoQ, or the Variation crosses the threshold set under Cl 37.1, the Contractor can set new rates, for details please refer ▬►[PPMO: SBD for Bridge, GCC Clouse 39.2: Payments for Variations. ]