Step 2: Procedure for Dispute

As per Cl 25.1, if the Contractor considers that a decision taken by the Project Manager was either outside his authority or wrongly taken, the decision shall be referred to the Adjudicator within 14 days of the notification of the Project Manager’s decision for detail please refer▬►PPMO: SBD for Bridge, GCC Clouse 25.1: Procedure for Dispute .