Step 6: Extension of the Intended Completion Date

Cl 27.1 requires that the Project Manager (with the Project-in-Charge’s agreement) shall extend the Completion Date if a Compensation event occurs which makes it impossible for Contract completion to be achieved by the Completion Date without the Contractor taking steps to accelerate the work, and which would cause the Contractor to incur additional cost. With respect to granting a time extension, the Project Manager shall make a decision in this regard within 21 days of the Contractor requesting the Project Manager’s decision, for detail please refer▬►PPMO: SBD for Bridge, GCC Clouse 27.1 Extension of the Intended Completion Dtae.