Step 3: Determination Of Fee
The Engineer determines fee when such change reduces in the contract value of this part refer▬►Sub-Clause 3.5 Determinations and the fee is included in the Contract Price however the fee shall be half of the difference between (i) reduction in contract value resulting from change (excluding adjustment under (1) Sub-Clause 13.7: Adjustments for Changes in Legislation and (2) Sub-Clause 13.8: Adjustment for Changes in Cost) and (ii) the reduction (if any) in the value to the Employer of the varied works, taking account of any reductions in (a) quality, (b)anticipated life or operational efficiencies. And if amount (i) is less than amount (ii), there will not be a fee.