Step
|
Activity
|
Responsibility
|
Time *
|
1
|
Preparation of Terms of reference for a Feasibility Study
|
Preparation: Project Manager
Approval: Departmental Head
|
0.5 month
|
2
|
Appointment of Feasibility Consultant
|
Processing: Project Manager
Approval: (Refer PWD I-9)
|
Up to 6
months
|
3
|
Development of Project Objectives and Scope
|
Consultant or Project Staff
|
0.5 month
|
4
|
Data Collection
|
Consultant or Project Staff
|
0.5 month
|
5
|
Development of Project Works
|
Consultant or Project Staff
|
0.5 month
|
6
|
Stakeholder Participation
|
Consultant or Project Staff
|
2-3 months
|
7
|
Preliminary Engineering
|
Consultant or Project Staff
|
2-3 months
|
8
|
Preliminary Cost Estimate
|
Preparation: Consultant or Project Staff
Approval: (Refer PWD I-9)
|
1.0 month
|
9
|
Economic and Financial Analyses
|
Consultant or Project Staff
|
0.5 month
|
10
|
Identification of Institutional and Training Requirements
|
Consultant or Project Staff
|
0.5 month
|
11
|
Proposed Implementation Modalities
|
Preparation: Consultant or Project Staff in consultation with Project Manager
|
0.25 month
|
12
|
Proposed Funding Modalities
|
|
0.25 month
|
13
|
Assessment of Project Risks
|
Executing agency or donor
|
0.5 month
|
14
|
Initial Implementation Plan and Schedule
|
Executing agency
|
0.5 month
|
15
|
Feasibility Report
|
Preparation: Consultant or Project Staff in consultation with Project Manager
|
-
|
|
Total Elapsed Time
|
All
|
Up to 12
months
|