Step 6: Stakeholder Participation
Consultation shall be carried out with the project stakeholders including users of the project works, local bodies, central government agency and other those involved on projects that will affect or be affected by the proposed project
2.2 Steps in a Feasibility Study
Table 2.1 Steps in a Feasibility Study
Step |
Activity |
Responsibility |
Time * |
1 |
Preparation of Terms of reference for a Feasibility Study |
Preparation: Project Manager Approval: Departmental Head |
0.5 month |
2 |
Appointment of Feasibility Consultant |
Processing: Project Manager Approval: (Refer PWD I-9) |
Up to 6 months |
3 |
Development of Project Objectives and Scope |
Consultant or Project Staff |
0.5 month |
4 |
Data Collection |
Consultant or Project Staff |
0.5 month |
5 |
Development of Project Works |
Consultant or Project Staff |
0.5 month |
6 |
Stakeholder Participation |
Consultant or Project Staff |
2-3 months |
7 |
Preliminary Engineering |
Consultant or Project Staff |
2-3 months |
8 |
Preliminary Cost Estimate |
Preparation: Consultant or Project Staff Approval: (Refer PWD I-9) |
1.0 month
|
9 |
Economic and Financial Analyses |
Consultant or Project Staff |
0.5 month |
10 |
Identification of Institutional and Training Requirements |
Consultant or Project Staff |
0.5 month |
11 |
Proposed Implementation Modalities |
Preparation: Consultant or Project Staff in consultation with Project Manager |
0.25 month |
12
|
Proposed Funding Modalities |
0.25 month |
|
13 |
Assessment of Project Risks |
Executing agency or donor |
0.5 month |
14 |
Initial Implementation Plan and Schedule |
Executing agency |
0.5 month |
15 |
Feasibility Report |
Preparation: Consultant or Project Staff in consultation with Project Manager |
- |
Total Elapsed Time |
All |
Up to 12 months |
* Time required for a major central level project. Time required for smaller projects should be no more than 1-2 months.
Step 1. Preparation of Terms of Reference for a Feasibility Study
While preparing the TOR for a feasibility study the following guidelines apply:
- The objective of the feasibility study shall be to investigate the technical and economic feasibility of the project so that a decision can be made regarding the scope and appropriateness of the project before proceeding with detailed engineering design.
- The scope of work for the study shall include the requirement to investigate feasible alternatives taking into account topography, geology, hydrology, environment, geotechnical and socio-economic factors. Alternatives should also be compared for various combinations of level-of-service standards. It is useful to mention in the TOR alternatives identified in the project identification stage.
- Order-of-magnitude estimates (±25%) of direct costs (land, construction and maintenance) are sufficient. These can be determined from reconnaissance field surveys and prevailing district rates. Cost analysis shall include standards, initial costs and life cycle costs.
- The depth of technical investigations, surveys and analyses shall be prescribed in the TOR. Mountain-specific aspects shall be duly considered for projects in mountainous regions.
- The benefits envisaged from the project that need to be evaluated in the economic analysis shall be clearly prescribed in the TOR.
- The feasibility study shall investigate other benefits and indirect costs and incorporate these in the economic analysis.
- The feasibility study shall include social and environmental assessments unless these are being conducted as separate studies. The findings and recommendations of the social and environmental studies shall be incorporated into the feasibility study cost estimates and economic analysis.
The recent policy statement of the NPC states that “all proposals for all new development projects funded by foreign donor agencies and all central level development projects funded by HMG/N shall include a logical framework from the beginning of fiscal year 2000/2001”. An example of the proposed logical framework is presented below:
Project Title: |
||||
Narrative Summary |
Objectively Verifiable Indicators (OVI) |
Means of Verification (MOV) |
Key Assumptions |
|
Goal |
||||
Purpose |
||||
Outputs |
||||
Activities |
||||
Inputs |
A set of criteria presented in terms of quantity, quality, time and cost which will indicate in concrete terms that the expected results are achieved. The indicators should be presented in measurable terms stating baseline and target values as well as the time frame for their achievement.
The monitoring mechanism in a project such as specific reports and site visits by the Project Manager, donor or other monitoring agencies.
External conditions that could affect the progress or success of the project and which are outside of the control of the project. If these conditions change, they may adversely affect the delivery of project objectives. They should be considered as the risk associated with the project and should be evaluated separately.
Feasibility studies invariably require a wide variety of information in the form of mapping, field surveys, design standards and unit costs for the preliminary engineering design as well as socio-economic data for estimating benefits and impacts. The data collection at the feasibility stage should be consistent with the size and complexity of the of the project. The following guidelines apply:
- Maximum use should be made of secondary data from existing government and other sources and expert estimations. HMG/N should provide all the related data available.
- The consultant should collect related data from other agencies and all pertinent technical standards and guidelines for the type of works under study.
- The area affected by the project should be estimated, and agreed with stakeholders as part of the data collection phase.
- Available data shall be compiled and the data gaps identified.
- The consultant shall recommend a methodology how to collect the additional data needed for the feasibility study. Primary data collection requiring field surveys at the project site should be done by sampling only.
- Formats/questionnaires/checklists for primary data collection shall be prepared.
- Primary data shall be surveyed in the field using the formats developed.
- The field survey shall be sector-specific as described in Part II, Chapters 18 to 26.
- Data collected shall be assembled in a database and maps suitable for feasibility-level analysis and costing.
- Design criteria shall be based on the functional, structural and environmental requirements in consultation with stakeholders.
- Evaluation criteria shall be developed and used to rank feasible alternatives.
Table 2.3 Typical Data Requirements
Main Data Groups
|
Typical Data Requirements
|
Project affected area characteristics |
Base map – showing settlements, roads, buildings, irrigation, utilities, administrative boundaries Demographic data – population characteristics Economic data – agriculture, industries, employment Environmental map – natural resources, cultural heritage |
Demand and capacity characteristics |
Historic demand related to the proposed project Forecast of demand Level of service policy and criteria |
Economic indicators in project affected area |
Population forecast Economic activity measures and forecasts |
Engineering data at the project site |
Topographical map Land survey as needed Geology and hydrology Soil conditions Sources of construction materials |
Preliminary engineering design and cost estimates |
Design criteria and standards Unit prices of materials and labour Construction norms |
Economic and financial analysis |
Taxes, duties, shadow prices of project inputs and economic production in project area Discount rate Income levels |