Step 15: Feasibility Report
After completion of
all the above steps, the feasibility report shall be prepared containing all
the outputs of the feasibility analysis including social and environmental
assessments. The report shall be compatible with government financial acts and
regulation, for detailed guidelines
refer
▬►PWD Part
II Procedural Directives, Volume A General Procedures, Chapter2, Feasibility
Studies,Step-14 Pages 2-9,
Step 14. Initial Implementation Plan and Schedule
An initial implementation plan and schedule shall be developed in consultation with the takeholders. The following contents are suggested:
- A summary of the project objectives and components.
- A Gantt chart showing key activities and milestones.
- The Gantt chart should identify dependencies. Where appropriate, a critical path network may be drawn showing the dependencies and identifying the critical path.
- The human, material and capital resources assigned to activities and their schedule.
- The implementation schedule should be designed with sufficient flexibility to accommodate delays in individual tasks without jeopardising the overall project objectives, funding constraints and completion date.
- The proposed organisational arrangements.
- A summary of proposed funding arrangements.
- The major recommendations on project implementation procedures.
The implementing agency will develop a more detailed implementation plan after the project has eceived approval and before proceeding with implementation. Guidelines for the preparation of his detailed plan are contained in Part II Chapter 6 Project Implementation Plan.