Step 14: Initial Implementation Plan and Schedule
Develop programs of
works, resource schedules and milestones for implementation of the proposed
projects, for detail guidelines
refer
▬►PWD Part
II Procedural Directives, Volume A General Procedures, Chapter2, Feasibility
Studies,Step-14 Pages 2-9, and Chapter 6: Project Implementation Plan Page 6-1.
Step 14. Initial Implementation Plan and Schedule
An initial implementation plan and schedule shall be developed in consultation with the takeholders. The following contents are suggested:
- A summary of the project objectives and components.
- A Gantt chart showing key activities and milestones.
- The Gantt chart should identify dependencies. Where appropriate, a critical path network may be drawn showing the dependencies and identifying the critical path.
- The human, material and capital resources assigned to activities and their schedule.
- The implementation schedule should be designed with sufficient flexibility to accommodate delays in individual tasks without jeopardising the overall project objectives, funding constraints and completion date.
- The proposed organisational arrangements.
- A summary of proposed funding arrangements.
- The major recommendations on project implementation procedures.
The implementing agency will develop a more detailed implementation plan after the project has eceived approval and before proceeding with implementation. Guidelines for the preparation of his detailed plan are contained in Part II Chapter 6 Project Implementation Plan.