Step 6: Preparation of Bidding Document

Bidding documents shall be prepared as per the Standard Bidding Document (SBD) developed and prescribed by PPMO. It may be the SBD for small, medium or large contracts depending on the size or nature of the Bridge Works. The bidding documents would generally contain Instruction to Bidders (ITB), Bid Data Sheet, Evaluation and Qualification Criteria, GCC and SCC, Technical Specification, Drawings and BOQ as well as Bank Guarantee Securities formats for details, Refer ▬► PPA -2007, Chapter 3, Section 13, PPR -2007, Chapter 5, Rule –(37,38, 39, 40, 41, 42, 43, 45, 46 );SBD (for medium contract for construction of bridge) Section III Heading C Preparation of Bids clause 11 to 18 ; PWD Vol-2, Chapter-9, Step 3, page 9-10,▬▼sample of bidding document for bridge works/Sunkoshi Bridge Bill of Quantities