Step 2: Routine Bridge Maintenance Budget Estimate

Establish the total length of bridges in each road link from the updated bridge inventory. Calculate the total number of length worker days required per road link using approved Norms. Similarly calculate the total cost estimate based on the district labor rates or wages fixed by the DoR per length worker and supervisor in Routine Worksheet Template of ARMP. The total cost estimate shall be the total of wages of lenght worker, supervisor, tools and minor repairs for 365 days

Refer ▬►ARMP templates, Part1 Procedures for Inspection and Maintenance of Bridges, sub-head 9: Recommended Activities to be Covered on Routine Maintenance page 12.