Step 9: Major Works Program
Bridge Project shall maintain a priority list for
construction of new bridges at national level. Design and cost estimation for
new construction shall be prepared by the Bridge Project. The Division shall
collect the cost estimate data from the Bridge Project at the time of ARMP
preparation and present cost estimates in the standard template of ARMP to forecast the
overall cost of works in the division. Similarly Division shall estimate the
budget required for on-going bridges and include it in the standard template of
ARMP, Refer ▬► ARMP Standard
2006 page 14
6.
Major Works Programme
Use for Major Rehabilitation, Reconstruction or Upgrading
programmes -selected at Regional level only
Guidance:
- Provide rationale of
required work (assessment, special report, photos etc.)
- Include new bridges,
bridge reconstruction, and other structures
- Any major works programme
that is ongoing, the Division must identify the funding already received, the
funding required for the coming fiscal year.
- Discussion with Regional
Directors at ARMP Regional workshop concerning necessity of work
- Detailed estimate per job
and programme per road link
- Summary estimate per link as
per table below
- Include Annual Works
Programme
- Include rate analysis in the
Annex to this document
- Note any other major works
being undertaken within the Division by DoR but funded by others, such as ADB,
World Bank.
|
Name of Road:
Programme: Rehabilitation
|
|
|
Road Link:
|
km:
|
Remarks
|
Location Chainage
|
Job (detailed estimate required for each job)
|
Unit
|
Quantity
|
NC/unit
|
Total NC
|
|
|
|
|
|
|
|
Ongoing
|
|
|
|
|
|
|
New
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Estimate
|
|
|
|
XXXX NC
|
|
Total Cost Estimate
of Major Works Programme
S.N.
|
Name of Road
|
Km
|
Proposed Budget
|
Remark
|
|
|
|
|
Ongoing
|
|
|
|
|
New
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Cost Estimate
|
|
|
|