Step 8: Resource Schedule
The Contractor shall provide a resource schedule covering the Labour,
Equipment and Materials required to undertake the activities shown in the
Program of Works: clearly indicating anticipated outputs, date of mobilization
of resources, details of storage facilities for materials etc. The resource
schedule shall be updated/revised to match any revisions of the Program of
Works refer ▬►Standard Specification for Road and
Bridges, Section 100 Sub-section 116
116. PROGRAMME
The Contractor shall provide all information needed for fulfillment of the programme and required in accordance with the Conditions of Contract including the sequence in which he intends to work including implementation of quality assurance plan. If the Contractor requests a change in the sequence and such change is approve by the Engineer, the Contractor shall have no claim as per the Conditions of Contract for delay arising from such revisions to the programme.
The programme for the construction and completion of the works shall be established using CPM/PERT techniques or equivalent. The programme shall be detailed enough to give, in addition to construction activities, detailed network activities for the submission and approval of materials, procurement of critical materials and equipment, fabrication of special products/equipments if any their installation and testing, and for all activities of the Engineer that are likely to affect the progress of work. The Contractor shall update all activities in accordance with the Conditions of Contract on the basis of the decision taken at the periodic site review meetings or as directed by the Engineer.
The programme shall also include the Contractor’s general requirements for any road closures pursuant to Clause 102 to be agreed in principle with the Engineer. Such agreement shall not relieve the Contractor of his responsibility to obtain specific approval for each closure or series of closures.
Any proposal for night working shall also be stated in the programme.