Step 27: As-built Drawing
The Contractor shall supply the As-Built Drawings by the dates stated in the SCC (i.e. 30days after completion of works), refer ▬►PPR-2007, Rule125, Sub-rule (1); SBD (for medium contract for construction of bridge)Section IV,GCC: Clause 57 Operation and Maintenance Manual,; PWD, Part-III, Medium Contract, Clause 58 Condition of Contract, page45, Contract Data 58.1 and 58.2 page 52
PPR - 2007, Rule 125
125. Work Completion Report to be Submitted:
(1) The concerned construction entrepreneur shall have to submit as built drawing to the Public Entity within thirty days of completion of construction works as per the procurement contract.
(2) After the expiry of defects liability period, the chief of the Public Entity shall prepare a work completion report by causing a technical staff to examine whether or not such construction works are carried out as per the approved drawing, design or specifications.
(3) The technical staff examining pursuant to Sub-rule (2) shall examine whether the completed work has been completed as per the approved drawing, design or specifications or not and shall have to submit a report thereof to the Public Entity.
(4) The concerned Public Entity shall have to submit the as built drawing under Sub-rule (1) and the work completion report submitted pursuant to Sub-rule (3) to the bid accepting authority and in cases where the chief of the Public Entity and the bid accepting authority is one and the same person, to one level higher authority to him/her.
(5) If the authority under Sub-rule (4) deems it necessary, s/he himself/herself may examine or cause to be examined through a technical staff or a team of technical staff the matter referred to in the work completion report.
(6) If, in examining pursuant to Sub-rule (5), the completed construction work is found to be consistent with the approved drawings, design or specifications, such authority shall have to approve such construction works.
(7) Notwithstanding anything contained in Sub-rule (6), if the examination work under Sub-rule (5) is not completed within forty five days from the date of submission of work completion report pursuant to Sub-rule (4), such construction work shall be ipso facto deemed to have been accepted.
(8) Notwithstanding anything contained elsewhere in this Rule, where the work completion report submitted pursuant to Sub-rule (3) is in respect of the construction work of up to one million Rupees, the chief of the concerned Public Entity may examine himself/herself if s/he is a technical staff and if s/he is not a technical staff may cause other technical employees to examine. In so examining or causing to be examined, if such construction work is found to have been constructed as per the approved drawing, design, s/he shall have to approve the work completion report, and give information on the approval of work completion to one level higher authority.
(9) After the work completion report is approved pursuant to this Rule, the Public Entity shall have to give work completion certificate to the concerned construction entrepreneur.
SBD
57. Operating and Maintenance Manuals
57.1 If “as built” Drawings
and/or operating and maintenance manuals are required, the Contractor shall
supply them by the dates stated in the stated in the SCC.
PWD Part III, Medium Contract, Clause 58 Condition of Contract
58. Operating and Maintenance Manuals
58.1 If “as built” Drawings and/or operating and maintenance manuals are required, the Contractor shall supply them by the dates stated in the Contract Data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract Data or the date instructed by the Project Manager, or they do not receive the Project Manager’s approval, the Project Manager shall withhold the amount stated in the Contract Data from payments due to the Contractor.