Step 19: Rate Variation

If the final quantity of work done differs from the BoQ quantity for any particular item by more than 25%, and provided that the overall change exceeds 2% (or otherwise if stipulated in the SCC) of the Initial Contract Price, the Project Manager or representative of the Project Manager shall adjust the item rate to allow for the change, but only with the Employer’s approval refer ▬►PPR-2007, Rule 118 Variation Order; SBD(for medium contract for construction of bridge)Section IV,GCC: Clause 37 and 38,; PWD, Part-III, Medium Contract, Clause 38, Condition of Contract, page39, Part-II, Medium Contract, Clause 38, Condition of Contract, page39., PWD, Part-II, Procedural Directives, Chapter 11: Construction of Works Sub-chapter 11.6.5,pages 11-13.