Step 28: Release Retention Money

The first half of the retention money shall be released to the Contractor after the issuing of the Defect Liability Certificate and the second half shall be released only after submission of the Tax Clerance Certificate, refer ▬► PPR-2007, Rule124; SBD (for medium contract for construction of bridge) Section IV GCC: clause 47 Retention; PWD, Part-III, Medium Contract, Clause 48 Condition of Contract,page43,Contract Data 48.1 page 51,