Step 7: Program of Works

The Contractor shall submit to the Project Manager a Program of Works after the date of Letter of Acceptance within specified date as in SCC for approval: this shall clearly show the general methods, arrangement, order, and timing for all activities within the Works. The program shall be updated and revised as required to show the effect of variation and compensation events if any, or to show recovery of progress slippage refer ▬►Standard Specification for Road and Bridges, Section 100 Sub-section 116; SBD (for medium contract for construction of bridge) Section IV GCC: clause 26 Programme; PWD, Part-III, Medium Contract, Clause 27, Condition of Contract, page37,Contract Data item No27.1 and 27.3,