Step 21: Update Securities and Insurances

With any approval of time variation (Extension of Time) the Contractor shall increase the validity of the Performance Securities as well as Insurances to cover the extended period of the completion of the contract up to end (+30days) of the Defect Liability Period refer ▬► PPR-2007, Rule 110,and 112 ; SBD (for medium contract for construction of bridge) Section IV GCC: clause 13 Insurance and clause 51 Securities; PWD, Part-III, Medium Contract, Clause 52, Condition of Contract, page44 and Clause 13 page 35,