Step 13: Quality Works

The Contractor is abide by the Contract Agreement to maintain and be responsible to provide specified standards for (a) workmanship,(b) quality materials and (c) finally quality works. The Contractor shall not be relived from its responsibility of the quality of the works even after approval of QAP. Correction of defects (noticed) during construction or Defect Notification Period shall still be the responsibility of the Contractor. And failure to correct the defects within agreed schedule shall attract appropriate Condition of Contract refer▬►Standard Specification for Road and Bridge, Section 504, ▬►SBD(for medium contract for construction of bridge)Section IV,GCC: Clause 32,33,34 and 35: Quality Control.