Step 2: Early Warning

Upon receipt notification of a claimed “Compensation Event” (whether for extension of time or additional costs) from the Contractor, the site engineer will acknowledge receipt to the Contractor, without commitment refer ▬► SBD (for medium contract for construction of bridge) Section IV GCC: clause 31 Early Warning; PWD, Part-III, Medium Contract, Clause 32.1, Condition of Contract,page38, .;